TEK1’s Steel Detailing for Sydney Metro – Resolving Design Challenges – 2
In the last blog in Sydney metro project , we discussed about the design issue regarding angle weld. Here we are going to discuss about the member placement issue. The design specified two PFCs on both sides of a column.Column was surrounded by fireproofing sheets. However, the PFC flanges clashed with the fireproofing sheets, making … Continue reading TEK1’s Steel Detailing for Sydney Metro – Resolving Design Challenges – 2